My Iris reported that TATA Power Company signed 2 contracts on June 20th 2009 with OPG Group, Chennai.
Under the first contract, TATA Power will provide operations and maintenance services to OPG Power Generation, for its 1x80 MW coal based power plant. This power plant is located at Gummidipoondi which is about 50 kilometers from Chennai city.
However, the contract is for an initial period of 2 years and can be extended with mutual consent. The plant is expected to be commissioned by September to October, 2009.
Under the second contract, TATA Power will provide project management services to OPG Power Gujarat for their upcoming 2x150 MW coal based thermal power plant. This plant will be located at Bhadreswar in the Kutch district of Gujarat and is likely to be commissioned by September 2011.