IRB Infra's SPV Commissions Yedeshi Aurangabad Highway

Infra News - Published on Fri, 22 Mar 2019

Image Source: steelguru.com
IRB Infra's SPV, Yedeshi Aurangabad Tollway Pvt Ltd, has partially commissioned its four laning highway project Yedeshi to Aurangabad, in the State of Maharashtra, on March 17, 2019; thus, throwing open all four lanes for vehicular traffic. The SPV is in possession of the Provisional Certification from the Competent Authority to commence tolling w.e.f. 17th March 2019, as it has completed 85.60% work of the project admeasuring 161.87 Kms, out of total length of 189 Kms. of the Yedeshi Aurangabad Section of NH-211. Accordingly, the SPV has started tolling on the project from 17th March 2019.

CMD Mr Virendra D Mhaiskar said “The newly widened highway will now have direct and quicker connectivity between two major cities of Maharashtra Solapur and Aurangabad; thus further smoothening the connectivity between South and North India. We hope that it would bring a boost to the economy of the region as well as a good traveling experience for both, passengers and goods transporters, with high safety added, 'This is our third BOT project commissioned successively after Kaithal Rajasthan Border Project in September 2017 and Solapur Yedeshi Project in March 2018 and now Yedeshi Aurangabad in March 2019; which demonstrates consistencies in project execution capabilities of the Company to bring better highway connectivity for developing India.”

Key features of the project:
Total project length 189.1 Kmssection on NH 211. The stretch connects the prime places in the State including Tulajapur and Osmanabad.
NHAI awarded this project under DBFOT pattern to IRB Infra for converting existing 2 lanes into 4 lanes, at a Project cost of Rs. 3,370 Crores
Project has Viability Gap Funding of Rs. 558 Crores from the NHAI
The project will have service road of 73.71 Kms; 18 pedestrian underpasses; 5 flyovers; 5 major bridges; 57 small bridges; 98 intersections; 194 culverts; and one railway over bridge along with 3 Toll Plazas
The Concession period for project is 26 years
Tolling commenced w.e.f. March 17, 2019 midnight
COD achieved in line with provisional certification issued by the Competent Authority