The 25 megawatt Kabeli B1 Hydropower project has started testing electricity generation. The power project lies in the Kabeli River which divides Panchthar and Taplejung districts. After the Kabeli Corridor conducted testing, the hydro power started testing power generation. Arun Kabeli Power Limited Director Mr Ramesh Neupane said preparations were on to start regular power generation within a month if the test production succeeded.

Mr Neupane said that “We have completed work from our side. Power will be evacuated to central transmission line after Nepal Electricity Authority gives us permission.”

Due to delay in the construction of the power project, construction cost had jumped to INR 5 billion from INR 4 billion.