Keys Handed Over for Chernobyl New Safe Confinement

Power News - Published on Mon, 15 Jul 2019

In a ceremony attended by Ukraine’s President Volodymyr Zelenskyy on the site of the former Chernobyl nuclear power plant the keys for the New Safe Confinement shielding the destroyed reactor 4 were symbolically presented to the Ukrainian authorities today. This marked the next step in the transformation of Chernobyl into an environmentally safe and secure state.

The handover also represented the completion of the largest ever example of international cooperation in the field of nuclear safety. The event was attended by the President of Ukraine, Volodymyr Zelenskyy, the Chairman of the Chernobyl Shelter Fund, Hans Blix, the EBRD Managing Director for Ukraine, Eastern Europa and the Caucasus, Matteo Patrone, the EBRD Director for Nuclear Safety, Balthasar Lindauer, and donor representatives.

Mr Lindauer said that “We are proud and pleased to see the completion of the New Safe Confinement. I would like to congratulate Ukraine on reaching this milestone and I would like to take this opportunity to thank those who have made this happen: the donors’ community, the EBRD and its shareholders, the international and local companies that turned the plans into reality, our experts from the Project Management Unit and the workforce which delivered this unprecedented achievement.”

The New Safe Confinement cost EUR 1.5 billion and was financed by 45 donor countries and institutions. It encloses the destroyed reactor 4, the unit destroyed by the 1986 nuclear accident at Chernobyl, and the provisional shelter built after the accident which still contains the molten core of the reactor and an estimated 200 tonnes of highly radioactive material.

The giant arch was constructed in two halves near the accident site from 2010 to 2016 and eventually slid over the damaged reactor. It is the largest moveable land-based structure ever built, with a span of 257m, a length of 162m, a height of 108m and a total weight of over 36,000 tonnes equipped with a crane system for future dismantling work.

The structure is the most prominent component of the EUR 2.1 billion Shelter Implementation Plan which included the completion of crucial infrastructure and safety projects, among others the stabilisation of the old shelter and the creation of the necessary infrastructure needed for the work at the Chernobyl site.