Maersk, DSV Panalpina, DFDS, SAS and Ørsted have formed the first partnership of its kind to develop an industrial-scale production facility to produce sustainable fuels for road, maritime and air transport in the Copenhagen area. The partnership brings together the demand and supply side of sustainable fuels with a vision to realise what could become one of the world's largest electrolyser and sustainable fuel production facilities. The project can spearhead the maturation of sustainable fuels while creating jobs and new value chains to reinforce Denmark's role as a green energy leader.

Copenhagen Airports, A.P. Moller - Maersk, DSV Panalpina, DFDS, SAS and Ørsted have brought together the demand and supply side of sustainable fuels in a unique partnership with the concrete vision to develop a new ground-breaking hydrogen and e-fuel production facility as soon as 2023. When fully scaled-up by 2030, the project could deliver more than 250,000 tonnes of sustainable fuel for buses, trucks, maritime vessels, and airplanes every year. Production would potentially be based on a total electrolyser capacity of 1.3 gigawatts, which would likely make it one of the world's largest facilities of its kind. The production from the fully scaled facility can reduce annual carbon emissions by 850,000 tonnes.

COWI and BCG act as knowledge partners for the project, and the project is supported by the Municipality of Copenhagen in line with Copenhagen's ambitious policies for decarbonisation. However, the partnership hopes that the project can, over time, act as a catalyst for similar projects in other parts of Denmark and internationally.

If realised as envisaged, the project will be located in the Greater Copenhagen Area and could supply renewable hydrogen for zero-emission buses tendered by Movia and heavy-duty trucks managed by DSV Panalpina, renewable methanol for A.P. Moller - Maersk vessels and renewable jet fuel (e-kerosene) for SAS airplanes and air transport out of Copenhagen Airports. The project will require a large-scale supply of renewable electricity, which could potentially come from offshore wind power produced at Rønne Banke off the island of Bornholm.

The electrolyser facility will not only be a potential cornerstone in decarbonising the partners' businesses but will also deliver a critical contribution to reaching Denmark's ambitious goal of reducing carbon emissions by 70% by 2030 compared to 1990 by replacing fossil fuels in heavy transport with sustainable fuels. The vision of the partnership is to develop the project in three stages:

The first stage, which could be operational by 2023, comprises a 10MW electrolyser which can produce renewable hydrogen used directly to fuel buses and trucks.

Stage two comprises a 250MW electrolyser facility which could be operational by 2027 when the first offshore wind power from Bornholm could be delivered. This facility would combine the production of renewable hydrogen with sustainable carbon capture from point-sources in the Greater Copenhagen area to produce renewable methanol for maritime transport and renewable jet-fuel (e-kerosene) for the aviation sector.

Stage three, which could be operational by 2030 when the offshore wind potential at Bornholm has been fully developed, would upgrade the project's electrolyser capacity to 1.3GW and capture more sustainable CO2, enough to supply more than 250,000 tonnes of sustainable fuels to be used in buses, trucks, maritime vessels and airplanes. The project has the potential to displace 5% of fossil fuels at Copenhagen Airport by 2027 and 30% by 2030.