Nevada Copper Pre-Commissions Grinding Circuit

Mining News - Published on Fri, 11 Oct 2019

Image Source: nevadacopper.com
Nevada Copper Corp confirmed that it has started pre-commissioning of the grinding circuit of the process plant at its Pumpkin Hollow underground copper project. Other recent milestones include completing the 120 kV power line and stockpiling over 70,000 tons of development ore on surface. The Company remains on target to commence production in Q4 2019 and to complete within its project cost estimate. Mr Matt Gili CEO of Nevada Copper said that we are now in the final stages before entering production in the fourth quarter of this year. I’m very proud of the team’s consistently high performance during this incredibly busy period and I know we are all excited by the upcoming transition from developer to producer.

The following milestones further prepare the Company for commencing concentrate production in Q4, 2019. Further construction details, including upcoming work, can be viewed on the Nevada Copper blog.
Pre-commissioning of the grinding circuit of the process plant has commenced.
120 kV power line is completed and energized to site.
The first Underground Project definition drilling program has confirmed high grade stope locations as per the resource model.
Flow through ventilation has been established between the 2850 and 2770 levels.
Over 70,000 tons of development ore has now been stockpiled on surface.