PNC Infratech receives provisional completion certificate for Aligarh-Moradabad Highway Project

Infra News - Published on Thu, 16 May 2019

Image Source: Hindustan
PNC Infratech announced the receipt of 'Provisional Completion Certificate' for one of the national highway projects executed by the Company -Improvement/Augmentation of 146.4 km long Aligarh-Moradabad Section of NH-93 to two lanes with paved shoulders, in the state of Uttar Pradesh under NHDP Phase IV on EPC Mode with effect from 13 May 2019.

As the project has been completed seventy-three (73) days ahead of the scheduled completion date of 25 July 2019, the Company has become entitled for early completion bonus @ 0.03% of the Contract Price (Rs. 644.5 crore) for each day of ahead of scheduled completion in terms of the agreement executed with National Highways Authority of India.