Update on Construction of Alba Spent Pot Lining Treatment Plant

Metal News - Published on Fri, 19 Jun 2020

Image Source: Alba Spent Pot Lining Treatment Plant
Aluminium Bahrain Spent Pot Lining Treatment Plant construction is progressing as per schedule. The Project’s overall progress advanced by more than 21% and achieved over 35,078 working hours without LTI by May-end 2020. The SPL Treatment Plant, expected to be operational by Q1 2021, will have the capacity to treat 30,000 to 35,000 tonnes of SPL a year, which, after being processed, can be used in other industries.

In line with Bahrain’s National Waste Management, this project will provide a value-creating and sustainable solution to treat SPL with ensuring zero-waste.

Source :

Posted By : Yogender Pancholi on Fri, 19 Jun 2020