First unit of coal based Kalisindh thermal power plant has commenced generation

Steel News - Published on Tue, 25 Mar 2014

The first unit of Coal based Kalisindh Super Thermal Power Plant in Jhalawar district has commenced generation. Run by the Rajasthan Rajaya Vidyut Utpadan Nigam Limited, the plant has been synchronised and power generation started.

The boiler of the first unit with the capacity of 600 MW power generation was light up on March 6th but could not be synchronized due to technical reasons and the efforts were on for same since then.

Mr S S Meena, Chief engineer of Kalisindh Super Thermal Power Plant, said that the first unit of the plant was synchronised night and power generation has started.

First unit of coal based Kalisindh thermal power plant starts power generation First unit of coal based Kalisindh thermal power plant starts power generation

He said in the first week that 200 MW to 250 MW power would be generated by operating the unit with Heavy Furnace Oil.

As the plant is thermal based, the unit will subsequently start generating power with coal fuel with its full capacity of 600 MW.

He said that \"After power generation of 60% load, the unit would automatically generate power with coal fuel replacing Heavy Furnace Oil, full generation in the first unit is expected to be achieved by the end of this month.”

He said that efforts are also on to expeditiously light up the second unit of the plant under the supervision 20 Chinese engineers.

He added that \"We intent to achieve our proposed target of generating 1,200 megawatt of power with both the units by June this year?”

Kalisindh Super Thermal Power Plant would be the third such plant under Rajasthan Rajaya Vidyut Utpadan Nigam Limited after the ones in Kota and Chabra in Baran district.

Source – IBN Live

( www.powerguru.in)