Pakistan government to launch interconnection of Thar Coal with NTDC

Steel News - Published on Thu, 01 Mar 2012

Business Recorder reported that the government will launch Interconnection of Thar Coal based 1200 MW Engro Power Plant with National Transmission & Despatch Company system\' project at a cost of PKR 22.04 billion with the objective of providing consistent power supply to industrial, agricultural, commercial and domestic consumers.

The cost includes PKR 14.845 billion Foreign Exchange Component and PKR 7.19 local component. The project is likely to be financed by Japan International Cooperation Agency or through Irish Credit Bureau on buyer\'s credit basis and sponsored by the NTDC.

The location of the project is District Matiari, Sindh and it is aimed at providing adequate facilities for reliable and stable transmission of electrical power, keeping in view the growing demand of domestic, commercial, industrial and agricultural customers of Discos.

The project would disperse bulk power from 1200 MW Engro Power at Thar to up country by constructing 500kv D/C transmission lines, 250 kilometers long from the power plant at Thar to Matiari with extension at existing 500 KV grid station of Matiari.

Thar Coal Energy Board has been established to promote and facilitate the public and private sector coal industry. Thar coal deposits have been rapidly recognized as a major energy resource with the potential to transform the energy equations in the country. Therefore, initially the intent is to develop Thar coal mine for generation of electricity from two 1200 MW Power Plants one by Engro in private sector and another in public sector by PEPCO.

Ministry of Water and Power had decided in a meeting of Thar Coal Energy Board that NTDC would immediately prepare a work plan for providing the inter connection arrangements for dispersal of power of these power plants.

According to the document the NTDC has planned a transmission scheme for evacuation of power from 1200 MW Engro Power Plant with the following scope: considering that the proposed third 500 KV Jamshoro Moro RY.

Khan Transmission Line and 850 MW Wind Power plant is constructed before its completion. A MoU between PEPCO and Sindh Engro Coal Mining Company for detailed feasibility study had been signed.

Sindh Engro Coal Mining Company has carried out detailed feasibility study for coal mining for both power plants. The expected date of completion of the coal mining project is December 2015 while the two Thar coal based power plants of 1200 MW each is 2015 to 2016.

According to official sources, High Voltage Direct Current transmission lines will be required for evacuation of additional generation at Thar in the year 2015 to 2016 and onward as well as the power generated from the proposed power plant.

They said that in case future generation at Thar does not mature during the next two years while AES imported coal power plant and 1000 MW import of power from Iran does mature then 525km single circuit AC transmission line from Matiari to RY Khan would be required in future for the dispersal of this power.

(Sourced from Business Recorder)